The Lisle Library's renovation project

 began on September 4, 2007. The first

 indication that something was happening 

was the sign going up at the 

west entrance.

Renovation Sign Supplies were delivered. In the first week 

the east entrance was excavated to prepare 

it to become the new main entrance.  Concrete 

footings were poured and electricity was installed 

for new lighting.

Supplies at the East Entrance Excavation at the East Entrance The Concrete Footings for the East Entrance Extension
Temporary East Entrance During the first phase of the renovation, 

entry on the east end was through the 

meeting room. The framing was done to 

move the exterior door to the far edge of t

he building. The book drop is installed in 

the stone pillar.

Framing out the East Entrance Extension
Construction of East Entrance Extension  The Book Drop Foyer unser construction
Foyer being tiled Inside, the foyer was tiled. The pay 

phone was reinstalled. The ceiling 

tiles were replaced.  Work was done 

to completely refit the restrooms.

 

Nearly-finished foyer
New light fixtures in the foyer The new light fixtures go up and 

the drinking fountains installed. On 

January 25th the carpet was installed.

Drinking fountains
Preparations begin to carpet the foyer. The foyer's carpet mosaic takes shape. The finished foyer